The winners of Hungary`s first technology neutral-tender were announced
Solar developers were awarded 131.4 MW of the capacity in the auction, biomass installation accounted for the remaining 500 kW of capacity. MEKH preselected 186 energy projects for the procurement exercise. The awarded 131.4 MW of solar accounts for 60 projects with 42.8 MW of installations ranking between 300 kW and 1 MW.
In the first category, the final average price was HUF 24.81/kWh and HUF 21.69/kWh in the second. A 20 MW solar plant received the lowest bid , in the value of HUF 20.20/kWh.
The list of the selected 72 projects can be found here: https://lnkd.in/dNbu5ye
More information at: https://lnkd.in/dt2NWyZ